Downtown Reconstruction


Project Overview

The Downtown Project consists of reconstruction of streets, sanitary sewer, storm sewer and some watermain. Additional streetscape items such as trees, planters, benches and kiosks will also be constructed as part of the project.

The project area includes Front St from South 6th to South 8th, Laurel St from South 6th to South 8th, South 7th from Maple to Laurel, and the alleys in these areas.

The project consultant for the project is Widseth Smith Nolting and SRF Consulting. The general contractor for the project is Toms Backhoe Service of Brainerd.

Construction is scheduled to begin April 20, 2009, weather permitting, and be completed by July 31, 2009.

Project Location Map
Project Schedule (3/31/09)
Streetscape Design

Weekly Newsletters

Each week the Contractor will provide a newsletter to let businesses and visitors know the various construction details of the project for the upcoming week.

Project Contacts

Should you have any questions or concerns about the Downtown Reconstruction project, contact one of the following;

Owner
Jeff Hulsether
City of Brainerd
City Engineer
501 Laurel Street
Brainerd, MN 56401
218-828-2309
jhulsether@ci.brainerd.mn.us
Project Engineer
Tim Houle
Widseth Smith Nolting
Project Engineer
7804 Industrial Park Rd
Baxter, MN 56425
218-829-5117
Contractor
Tom's Backhoe Service
Tom Thompson
Superintendent
323 Woodland Hills Lane
Brainerd, MN 56401
218-828-4232

Additional Info:

www.DowntownBrainerd.com - A website developed by the Brainerd Lakes Area Chamber of Commerce to help Downtown businesses and visitors become familiar with the construction and improvements for the area.