Construction Projects - 2017 Season

2017 Chip Seal Project -

Improvement 17-02


Chip Seal Project begins Wed 5/24 and will take approximately two days to complete.

    

Map: 2017 Chip Seal Project


 
Airport Utility Extension - Improvement 14-15


Project limits are generally along the State Highway 210 corridor between East Street and the Brainerd Lakes Regional Airport, and along the East Street corridor from TH 210 to the Evergreen Interceptor west of 1st Avenue Northeast.

Project elements include the construction of new water and sanitary trunk lines along State Highway 210, reconstruction and rehabilitation of the existing trunk sanitary sewer system under E Street between the north-south interceptor west of 1st Avenue Northeast to the 8th Avenue Northeast/Mill Avenue intersection area, and the construction of a water booster station and multiple sanitary lift stations in Lum Park and along the State Highway 210 corridor to operate the system under design flows.

Construction is currently under winter suspension.  Work will continue and be completed in the Spring of 2017.
  
You can see more about the Airport Utility Extension Project by visiting Short Elliot Hendrickson's (SEH) website at http://www.sehinc.com/online/brd.  Here, you can find monthly project update memos, a project map, and the original Basis of Design Report.

​Jackson Street - City Improvement 14-03 - SAP 108-129-002

The City of Brainerd and the Contractor, Tri-City Paving, Incorporated will be working together to resurface Jackson Street from NW 4th Street (Riverside Drive) to the Brainerd City Limits.

Work will include removing the old pavement and gravel, re-grading the subgrade, placement of new gravel base, and placing a new bituminous surface.  Minor driveway, curb and gutter, and approach work will also be done as part of the project.

A sidewalk is planned to be incorporated as part of the project on the south side of the street.  There will also be bike lanes added as part of the project, and parking eliminated on both sides of the street.

​Construction Detour

A detour is planned for this work on Jackson Street and includes Baxter Drive, State Highway 210, and NW 4th Street (Riverside Drive).  The route will be open for local traffic to traverse through the work zone.

Construction Schedule


The Contractor is paving the final course of asphalt the week of July 3rd, 2017.  The striping and signage along the route will be completed the week ending July 15, 2017.  

Buffalo Hills Lane - City Improvement 16-13 - SAP 108-136-003

The City of Brainerd and the Contractor, Tri-City Paving, Incorporated will be working together to resurface Buffalo Hills Lane from S 6th Street to Graydon Avenue.

Work will include removing the old pavement and gravel, re-grading the subgrade, placement of new gravel base, and placing a new bituminous surface.  Minor driveway, curb and gutter, and approach work will also be done as part of the project.

​Construction Detour

A detour is planned for this work on Buffalo Hills Lane and includes the use of Crestview Lane, Woodland Hills Lane, Greenwood Street, and Business 371.

Construction Schdeule


The work on Buffalo Hills Lane will begin on July 10, 2017 with removals of the existing pavement and gravel.  Concrete work and gravel placement will also commence on July 12, 2017 and continue through July 21, 2017.  Paving on Buffalo Hills Lane will begin on July 24, 2017 and continue through July 28, 2017.  When paving and striping are completed, the road will be opened back up to through traffic.  Final completion is scheduled for August 5, 2017.

The road will be open to local traffic throughout the construction.

Oak Street - City Improvement 14-01 - SAP 108-113-007

The City of Brainerd and the Contractor, Tri-City Paving, Incorporated will be working together to mill and overlay Oak Street from S 6th Street and SE 19th Street.

Work will include milling of the existing pavement surface and placement of a new bituminous surface to correct rutting issues in the current pavement.

All ADA sidewalk curb ramps are being replaced as part of the project.

​Construction Detour

No construction detour is planned for Oak Street.  However, traffic on side streets may have limited access to Oak Street at different times during construction along with Oak Street having shoulder closures throughout the project.

Construction Schedule


Milling on Oak Street began on June 14th, 2017.  The Contractor will continue with the removals and replacements of the sidewalk ramps through July 14, 2017.  The Contractor will mill the remaining portions of the street once work on sidewalk ramps are completed.  Paving is scheduled for the week of July 24th.  Final completion is scheduled for August 5, 2017.

Through traffic will be allowed through the construction site.  Please use caution around the equipment and watch for project personnel when traversing through the project.